The original item was published from 4/10/2019 4:22:00 PM to 5/2/2019 12:00:17 AM.

News Flash

Road Projects

Posted on: April 10, 2019

[ARCHIVED] 16th St (Oakes Rd - STH 31)

16TH Street Phase 1 190409

Installation of the new water main on 16th St continues east, and is now crossing Emmertsen Rd. The contractor will be providing a 48-hour notice prior to any temporary driveway & road closures as the water main work progresses. Temporary closures should reopen at the end of the same day.

Most of the grading work on 16th St between Emmertsen Rd and Oakes Rd has been completed. Work on infiltration basins will continue as soon as utility relocates have been marked/flagged.

Rough grading on the south side of 16th St; between Emmertsen Rd and STH 31, has been done to allow additional room for traffic during the water main installation. The remainder of the storm sewer will be installed prior to the water main crossing STH 31.

A weekend closure of STH 31 will be in place when the water main is installation work is being done across STH 31.

Facebook Twitter Email

Other News in Road Projects

Image of a road with Orange Barrels

WIS 31 RECONSTRUCTION PROJECT

Posted on: November 10, 2025 | Last Modified on: November 10, 2025
  1. Mount Pleasant, Wisconsin

Contact Us

  1. 8811 Campus Drive
    Mount Pleasant, WI 53406
    Ph: 262-664-7800
    Fx: 262-664-7801


    Village Hall Hours
    Monday thru Friday
    8:00 AM to 5:00 PM


    Friday
    First full week of May through the last full week of September
    8:00 PM to 1:00 PM


    Court Office Hours

Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow