As of June 19, 2024
Section 1: Emerald Dr, Prairie Ridge Dr, & Woodland Hills Dr
Prepping road surface and utility structures for the final surface.
Section 6: Cottage Dr
Saturday, June 22 - Roadway scheduled to be pulverized. Work to continue Monday.
Section 2: Leslie Ann Ln, Newport Ln, Weatherwood Ln, & White Oak Ln
Curb and gutter spot repairs have started.
Section 3: Nature Trl, Pineview Ct, Quiet Valley Ct, Homewood Ct, and Wilderness Dr
Curb and gutter spot repairs have started.
Curb and gutter spot repairs will continue to the remaining sections once sections 1 & 2 are complete. Please note that weather can impact all schedules. We appreciate your patience and cooperation as we complete our paving projects.
View the full paving program.