As of July 29, 2024
Section 1: Emerald Dr, Prairie Ridge Dr, & Woodland Hills Dr
All work in Section 1 is complete.
Section 2: Leslie Ann Ln, Newport Ln, Weatherwood Ln, & White Oak Ln
The road surface has been pulverized. Manhole and catch basin repairs are ongoing. New pavement installation is scheduled for early next week.
Section 3: Nature Trl, Pineview Ct, Quiet Valley Ct, Homewood Ct, and Wilderness Dr
The road surface has been pulverized. Manhole and catch basin repairs are ongoing. New pavement installation is scheduled for early next week.
Section 4: Summerset Dr
No update is available at this time.
Section 5: Regency Hills Dr, Burr Oaks Dr, Short Valley Ln, Royal Oaks Dr, Hillside Dr, Providence Dr, & Kristy Ct
Curb and gutter spot replacement has started. Road pulverizing is scheduled to start the week of August 12.
Section 6: Cottage Dr
All work in Section 6 is complete.
Section 7: Biscayne Ave
Curb and gutter spot replacement has started. Road pulverizing is scheduled to start after Section 5.
Section 8: Taurus Dr
No update is available at this time.
Please note that weather can impact all schedules. We appreciate your patience and cooperation as we complete our paving projects.
View the full paving program.