As of August 29, 2024
Section 1: Emerald Dr, Prairie Ridge Dr, & Woodland Hills Dr
All work in Section 1 is complete.
Section 2: Leslie Ann Ln, Newport Ln, Weatherwood Ln, & White Oak Ln
All road work in Section 2 is complete. Final restoration and landscaping is underway.
Section 3: Nature Trl, Pineview Ct, Quiet Valley Ct, Homewood Ct, and Wilderness Dr
All road work in Section 3 is complete. Final restoration and landscaping is underway.
Section 4: Summerset Dr
Road pulverizing is scheduled to start on August 29.
Section 5: Regency Hills Dr, Burr Oaks Dr, Short Valley Ln, Royal Oaks Dr, Hillside Dr, Providence Dr, & Kristy Ct
Road is being prepped for final surface. New pavement installation is scheduled for September 3.
Section 6: Cottage Dr
All road work in Section 6 is complete. Final restoration and landscaping is underway.
Section 7: Biscayne Ave
Road paving is scheduled for August 30.
Section 8: Taurus Dr
Road pulverizing is scheduled for August 29.
Please note that weather can impact all schedules. We appreciate your patience and cooperation as we complete our paving projects.